What kills a data center project?
The reasons for **cancellations** differ markedly from the reasons for **delays**
The main factors in project cancellations are community opposition (52%) and permitting issues (30%)
Delays are mostly caused by construction issues (36%), power and grid (15%) or tenant/offtake (12%)
Developers will often cancel a project and move on to another site to escape community opposition, while they’re willing to wait for equipment and power
The reasons for **cancellations** differ markedly from the reasons for **delays**
The main factors in project cancellations are community opposition (52%) and permitting issues (30%)
Delays are mostly caused by construction issues (36%), power and grid (15%) or tenant/offtake (12%)
Developers will often cancel a project and move on to another site to escape community opposition, while they’re willing to wait for equipment and power
We polled 121 founders on their fundraising challenges and ran into what could be called the Climate Tech Paradox:
- 70% of founders say equity (venture or growth) would help them accelerate growth.
- 73% said VC isn't the right capital structure for them.
ctvc.co/2026-founder-s…
- 70% of founders say equity (venture or growth) would help them accelerate growth.
- 73% said VC isn't the right capital structure for them.
ctvc.co/2026-founder-s…
OpenAI confirmed it will anchor 8GW of the PORTS-Pike data center campus. Powering this is a planned 9.2GW natural gas plant (!!)
By generating capacity, this new plant would surpass the Grand Coulee Dam to become the largest power plant in the country, of any fuel type, and one of the largest gas plants in the world.
powerstack.currence.ai/p/powerstack-o…
By generating capacity, this new plant would surpass the Grand Coulee Dam to become the largest power plant in the country, of any fuel type, and one of the largest gas plants in the world.
powerstack.currence.ai/p/powerstack-o…
The media usually reads a hyperscaler capex increase as a signal for more AI capacity coming online. Our Q3 Data Center Outlook found it's mostly component inflation. Amazon's entire $20 billion guidance raise came down to memory costs alone.
currence.ai/blog/q3-2026-d…
currence.ai/blog/q3-2026-d…